The City of Plainfield has developed a list of “Shovel Ready” projects. The purpose of the Plainfield “Shovel Ready” list is to identify potential projects that may qualify for funding under the ARRA.  The “Shovel Ready “ list is not an application for funding,  rather it is a planning tool that can be used  to assist in applications for grant funding that will be available through various Federal and State  agencies.


Citizens should not be confused by various list’s circulating the internet.  These are just a list of potential projects and are not an application for funding.   There are links on these pages that will provide you with the appropriate websites to obtain information on stimulus funding. 


Currently, Federal and State agencies are in various stages of the developing their grant funding mechanisms to distribute ARRA funds.   One of the purposes of this website is to provide a communication tool that will identify the funding opportunities available and the action taken by the City of Plainfield to secure funding.


The City of Plainfield’s “Shovel Ready “ Project List


RECREATION PROJECTS

 Project Name

Project Description

“Shovel  Ready”

Estimated Cost

Madison Avenue Playground Improvements

The Construction of a bathroom facility at the Madison Park Playground

90 Days

 $              250,000.00

Seidler Field Bleacher Replacement

The replacement of old deteriorated bleachers

90 Days

 $              168,740.00

Youth Community Center

The rehabilitation or construction of Youth Community Center

180 Days +

 $          1,500,000.00

 

 

Recreation  Subtotal

 $          1,918,740.00

  

TRANSPORTATION PROJECTS


Project Name

Project Description

“Shovel  Ready”

Estimated Cost

Somerset Street - Road Rehabilitation

The rehabilitation of Somerset Street from the City limits to West Front Street

90 Days

 $               138,015.00

West 4th Street - Road Rehabilitation

The rehabilitation of  West 4th Street

90 days

 $               514,000.00

South Avenue - Road Reconstruction

The reconstruction of roadway on South Avenue Between Woodland Avenue and Terrill Road

90-120 Days

 $            2,000,000.00

Farragut Road –Rehabilitation

The rehabilitation of Farragut Road between the City limits and East Front Street

90 Days

 $               127,150.00

Hillside Avenue – Rehabilitation

The rehabilitation of Hillside Avenue between Berckman Street and Randolph Road

90 Days

 $               710,000.00

Employment Transportation Service

The creation of a van service to provide transportation services to warehouse employment center in South Brunswick N.J  not easily accessible through public transportation

180 Days

 $               210,000.00

Park Avenue - Corridor Improvements

The project will provide for upgrading three signalized intersections along Park Avenue

90 Days

 $               875,000.00

Terrill Road - Corridor Improvements

The project will provide for upgrading three  intersections along Terrill Road

90 Days

 $               810,000.00

Transportation Subtotal

 

 $            5,384,165.00